The contract crates leave in this order: how a breaking change lands across two repositories

The proposal holds the order and the policy. This appendix works two cases through it, one real and one hypothetical.

A real one, 2026-10-31 (UTC). jh7110_entropy pull request #5 renamed five constants and merged at 22:22 (partsfoundry/jh7110_entropy@535f79c). nife pull request #2979 opened at 22:27, moved the three manifests that pin the crate and the program that names the constants, and merged at 23:15. Fifty-three minutes end to end. nife's main never broke, because it pinned the old commit until the bump.

The contract case, worked for block_roster_contract after step 4: a hypothetical page change to version 2, with the durations the proposal measured.

  1. The contract repository merges version 2: VERSION = 2, magic blkrosv2, Cargo 0.2.0, a dated ledger entry. A trial run against nife's and disk-tools' current pins shows what breaks. About 7 minutes of the crate's CI.
  2. nife bumps its rev, and the kernel writes version 2. Its pull request names the landed commit. About 50 minutes through the merge queue.
  3. disk-tools bumps its rev, and disk_surveyor reads version 2.
  4. basalt moves the three pins in one pull request. The coherence check passes only with all three. About 10 to 15 minutes of gate.

The page is single-version, so step 4 is atomic. If basalt moved nife alone, the agreement check would refuse: the kernel serves (5, 2) and disk_surveyor declares (5, 1). A message contract serves N and N-1, so steps 2 and 3 may ship in different basalt bumps. As ยง201 (one roadmap until a citation has to cross) requires, the pull requests in steps 3 and 4 name what they wait for, and step 1 names nothing.