roadmap BUILT

94. The untracked-work sweep, and the convention that ends the category

Built 2026-08-18. Deliverable one landed 2026-08-04 (PR #91, with the minting in PR #94) in all three of its parts. The sweep ran, the TODO lint landed, and the inventory is notes/untracked-work-sweep.md. Each of the nine recorded-accepted findings carries its blessing in the paragraph a reader meets the limitation in. Deliverable two waited fourteen days for one edit a lane may not make. Its conventions were drafted in this block on 2026-08-04 and could not be landed from a lane, because a lane does not edit AGENTS.md. Nobody staged them for calef until 2026-08-18, when the maintainer put the drafted text up as a pull request and he approved it. The text below is what landed, verbatim.

That delay is this milestone's own failure mode, for the second time. Deliverable one's inventory sat in a pull request body for twelve days until the item-level list was gone and had to be re-derived. Deliverable two sat in a roadmap block for fourteen, correctly filed and unactionable, because the block recorded what to do and nothing recorded who could do it. A proposal that only its author may enact is one assignment short of tracked. Raised 2026-08-03 by calef, completing 92 and 93's family. Those keep claims true. This one finds the work the tree has already identified but never gave a home, and then changes the working conventions so the category stops refilling.

What the sweep measured, kept because the numbers are the argument. 11 TODO-class markers and 29 notes with deferral phrasing were this block's predicted floor. The sweep corrected it to 11 hits of which 2 were real markers. git grep -w TODO is 82% false positives on this tree, which is what shaped the lint rather than a threshold anyone chose.

Two of the three parts of deliverable one were finished twelve days late, by this milestone's own failure mode. The inventory sat in PR #91's description and the nine blessings sat in a lane report. Both are the evaporating medium the block was written to drain, and neither is readable a fortnight on. The consequence was not hypothetical. The item-level list of the nine did not survive. So the nine now in the tree are the sweep's own rule applied a second time, and the note's BUGS section says so. A milestone that swept the tree for work with no home left its own findings without one, which is worth more as evidence than the sweep is as a deliverable.

The failure mode, with today's near-miss as the exhibit. Work gets identified in places that evaporate. A lane's final report ("worth a fix lane someday"), a pull-request comment, a commit message, a "follow-up, not built" aside in a decision block. Milestone 90 (A guard page under the per-CPU secondary stacks) exists only because calef happened to catch the guard-page finding of milestone 84 (stack high-water) in a report and said "add a milestone". Had he been away that day, the finding would be sitting in a merged PR's description, which nobody rereads. The BUGS convention is not the failure mode, and this milestone must not damage it. A recorded limitation living next to its feature is the FreeBSD posture working as designed. The defect is narrower: work someone actually intends, resting in a medium nobody will search.

Measured, as a floor not a count (predicted before the sweep, and the first half was wrong in the useful direction: 11 hits, 2 markers). There were 11 TODO-class markers in the Rust tree, and 29 notes containing "someday", "follow-on", "not built", or "deferred" phrasing. The real surface is larger (agent reports, DECISIONS follow-up asides like §26's signature variant, roadmap blocks' stretch items), which is what the sweep is for.

Deliverable one, the one-time sweep. Done; the record is notes/untracked-work-sweep.md. It swept code (TODO/FIXME class) and notes (the deferral phrasings, BUGS entries that are actually intended work rather than recorded limitations). It also swept DECISIONS follow-up asides and the roadmap's own stretch/later items. Every found item ends in one of the family's states. Minted as a milestone (integrator numbers at merge). Already tracked (link the milestone it lives in; dedupe, do not double-mint). Or recorded-accepted where it sits: a deliberate limitation, staying in BUGS on purpose, with the sweep's blessing recorded so 93's audits do not re-litigate it. "Noted" is not a state.

Deliverable two, the conventions. This milestone drafted them and calef landed them in AGENTS.md (a lane does not edit that file; the milestone's output is the proposed text). Its third convention landed as machinery in PR #91 and is the one that needed no prose:

  1. TODO markers in code cite their home or do not exist. script/lint gains a check that a TODO/FIXME names a milestone with a block, or fails. Done. A marker is the word with its punctuation attached; a mention is not. Markdown is exempt because prose explaining the convention has to spell the shape it forbids.

The first two are prose about how lanes and merges work, so they are AGENTS.md's and they are what remains outstanding. The text is written out here, ready to paste, rather than left in a lane report. A proposal that lives only in a report is the third instance of this milestone's own failure mode, and two were enough.

Proposed text, for AGENTS.md

Goes in the roles section, after the paragraph beginning "A developer's final report ends by handing off", which is the rule this one enforces.

Identified work leaves the lane in a tracked form, or the merge waits. A lane that finds work it is not doing may report it in exactly two shapes, and "worth doing someday" is neither. Either a proposed milestone (provisional, the integrator mints the number at merge like every other global name), or a recorded limitation written where a reader meets the feature, in the BUGS section beside it, which is what §71's promotion triggers are then measured against. A finding with no home is the integrator's cue to hold the merge until it has one.

This is rung three of the ladder, and it is worth naming why the lower rungs fail here specifically. A lane report is read once, by one person, on the day it is written. A pull request body is read while the diff is open and never again. Both feel like records while you are writing them, which is what makes this the failure that recurs: milestone 90 exists only because calef happened to be at his desk the day a report named it, and milestone 94 swept the tree for exactly this category and then left its own inventory in a pull request body for twelve days, by which point the item-level list was gone and had to be re-derived. See notes/untracked-work-sweep.md.

The merge checklist grows one line, in the same breath as pruning the worktree, deleting the branch and relinking nife-dev: every piece of identified work in the lane's report has a home.

Two things this deliberately does not do. It does not gate. No check can tell an intention from an observation in prose, and a lint that tried would be git grep -w TODO's 82% false-positive rate wearing a different hat. And it does not touch the BUGS convention, which is the FreeBSD posture working as designed. The whole point is to route intentions into it rather than out of it.

Scope note

One-time by design. The sweep clears the backlog and the conventions stop the refill. The recurring duty lands with 93's audits (whose sweeps will meet deferral phrasing in docs) and the lint gate (which meets it in code). If the sweep's minting produces a burst of small milestones, that is the mechanism working, not scope creep. The index absorbs them the way it absorbed 79 through 85 in one day. Convention text is drafted here, decided by calef, and its numbers in CLAUDE.md are his to place.

BUGS

Follow-on

Index row

The sweep ran and the lint landed. script/lint fails a TODO/FIXME that does not cite a milestone with a block. The measurement corrected the block's own floor (11 hits, 2 real markers; git grep -w TODO is 82% false positives here). Twelve findings that lived only in prose became milestones 100-111. Deliverable one is done. The inventory is notes/untracked-work-sweep.md, and each of the nine recorded-accepted findings carries its blessing in the paragraph a reader meets the limitation in. Outstanding, and calef's: deliverable two's two prose conventions never reached AGENTS.md. The text is written out in the block ready to paste