decisions DECIDED

247. The split begins with basalt holding nife, and procps moves first

Section number and slug provisional; the maintainer mints the number at merge. Written 2026-10-04 (UTC) by the lane lane/split-order-proposal. The options and their costs are in milestone 756 (procps, coreutils and util-linux are the first code to leave this repository); the measurements are in notes/the-first-split.md.

§151 (the goal of the repository split is independent release) ruled where the split ends and said its order "should be ruled on its own". This is that ruling. calef answered both questions on 2026-10-04 (UTC), relayed by the maintainer on pull request #1609.

The rulings

  1. basalt v0 is the first step. basalt pins nife whole at a commit and runs its image build and system test on all three architectures; nothing leaves this repository. The ruling includes the go-ahead for a lane's first write to nifeos/basalt. The manifest's file name and format ship provisional. Milestone 755 (basalt v0 pins nife and runs its gate) builds it.
  2. The first code cut is procps + coreutils + util-linux, and only once all six conditions hold:
    • milestone 610 (the interface's stability is measured weekly) carries the per-package co-change column §235 (the OS is built and updated from packages) requires before any move;
    • components is split so those programs are in crates of their own (milestone 691 (packages move out of this repository, one per pull request));
    • the cut builds without a clone of nife, through §235's S2 archive or a dated, recorded exception;
    • a crate may leave only when all of these hold (see the 2026-11-01 amendment below):
      1. it is classified under milestone 956 (the linked interfaces carry checkable versions): it carries an INTERFACE_ID and a version, or the record says it is not a format;
      2. it has a tagged release whose commit carries the Cargo version, and cargo-semver-checks --baseline-rev against that tag passes;
      3. nife consumes it as a git dependency pinned by revision with the version requirement stated, the form ruled for crates not yet published;
      4. a producer release can move each consumer's pin, by the mechanism of the proposal a-producer-release-moves-each-consumers-pin.md or an agreed manual step until it exists;
      5. the architect reads the crate's code by hand and reviews it before it leaves;
    • basalt takes a component's output as a package by digest (§235's P1, milestone 607 (nife is built and updated from packages) item 1);
    • the home and its repository name are ratified, and §201 (one roadmap until a citation has to cross)'s citation identity is ruled, since this cut is its revisit event.

Why, in one paragraph

Of the nine preconditions the records name, only the package format held on 2026-10-04: 157 breaking changes to the contract crates in four weeks, and 56 programs from 18 packages in one crate. basalt v0 needs none of them and builds the whole-system gate that §151's BUGS calls the real cost of a split, before any change has to land in two repositories. Among code cuts, procps and its neighbors had the fewest focused cross-package commits (5 of 11) and link the fewest moving interfaces. redoxfs was cheaper to move but more coupled, and preferring it would have been an effort argument.

What is not decided here

Amended 2026-10-06: the cut's packages are renamed

calef renamed the three packages of ruling 2 on 2026-10-06 (UTC): procps is process-tools, coreutils is core-tools and util-linux is disk-tools, and uuid moved from the last to the second. The cut holds the same fifteen programs, so the six conditions stand unchanged. The names above are the ones ruled on 2026-10-04 and stay as written. Milestone 756 (process-tools, core-tools and disk-tools are the first code to leave this repository) carries the new ones. The reasons are in each package's manifest and in notes/package-boundaries.md.

Amended 2026-11-01: condition 4 is a mechanism gate and a review

calef replaced condition 4 on 2026-11-01 (UTC), relayed on pull request #3033. No time-based measure remains: a crate whose interface still breaks may leave, and each break makes a new version and a new tagged release. The review in item 5 covers every crate at first, the first crate in particular. The architect generalizes feedback from those reviews into automated gates over time as patterns appear; the ruling does not say when, or whether, the manual review ends. The other five conditions and the destination stand. The crates now move bottom-up (milestone 756), so the four the original wording named are among those that move.